FULL BUILDING ASSESSMENT: Microsoft Silicon Valley Campus
The renovation and expansion project for Microsoft Silicon
Valley office campus aimed to increase campus capacity in
a sustainable way.
I was tasked with analyzing the embodied environmental
impacts generated over the life cycle of the building, with
regards to manufacture, transportation, construction, and
demolition. This involved an in-depth Life Cycle Assessment
(LCA) using Tally in Revit during the design and planning
process so that the data could influence design decisions.
The BIM model was imbued with the complete information
about the building materials and architectural products
that the structures will ultimately contain. This allowed the
design team to move from typologies and “rule of thumb”
environmental impact calculations to real-time assessments
at pivotal moments.